Scott CountyTop story
State regulators will hear the Hickory Grove power plant case in downtown Davenport starting Nov. 17
CIPCO's plant would cost about $400 million and add 240 megawatts
- $400 million
- estimated cost to build the plant
- 240 MW
- net output, around the clock
- 200
- jobs during construction
- 5 to 7
- permanent jobs at the plant
Source: Quad Cities Business Journal
If you want to see the Hickory Grove Generating Station debate up close, it's coming downtown. The Iowa Utilities Commission starts its evidentiary hearing at 9 a.m. Tuesday, Nov. 17, in the DoubleTree by Hilton ballroom, 111 E. Second St. Central Iowa Power Cooperative wants a 240-megawatt natural gas plant near Maysville, and the state commission now holds its fate.
Scott County supervisors rejected the zoning change 4-0 in February. CIPCO then filed for a state certificate on May 19. Supervisors, the Environmental Law & Policy Center and Concerned Citizens of Scott County are among those who'll be heard. Hearings run daily until all testimony is in.
- Calendar: runs through 5 p.m. Thu., Nov. 19
- Livestream: link is on the IUC hearing and meeting calendar
- Objection deadline: Mon., Nov. 16, at efs.iowa.gov (Docket GCU-2026-0001)
- Decision: expected a few weeks after the hearing
The Hickory Grove plant went from a county no vote to a state hearing
- Feb. 12Scott County supervisors vote against the zoning change.
- AprilThe IUC holds a public information meeting on the project.
- May 19CIPCO files its application for a generating certificate.
- Nov. 17The IUC evidentiary hearing begins at 9 a.m. in Davenport.
- Nov. 19The hearing is scheduled to run through 5 p.m.
- Spring '27Construction could start if the plant is approved.
- 2029The plant could become operational by the end of 2029 if approved.
Sources: Quad Cities Business Journal, KWQC, Business Record, WVIK